Spray Booth Effluent Treatment Plant Control System Upgrade

Modifications to PLC controls for the Spray Booth Effluent Treatment Plant Purge and Back Wash Cycle.

Project Details

  • Contract No. C109
  • Primary Service Construction & Commissioning, Detailed Design & Engineering, Implementation
  • Industry Automotive
  • Secondary Service As Built Documentation, Control Systems Engineering, Factory & Site Acceptance Testing, Pre-Commissioning & Commissioning, SCADA HMI System Engineering, Start Up Audit Start Up & Process Optimisation
  • Client Peugeot
  • Start Date Jun 2001
  • Consultant or EPC Industrial Design Industries
  • Contract Value ($) 5000
  • Project Location Pinley House, 2 Sunbeam Way, Coventry, CV3 1ND, United Kingdom
  • Person Hours 170
  • Execution Office Birmingham, United Kingdom
  • Status Completed

Scope of work

    Modifications to Spray Booth Effluent Treatment Plant control system.

Activities

  • PLC & HMI Control System Modifications
  • Site Software Sequence Modification
  • Site Testing
  • Commissioning
  • Conduct Start-up

Deliverables

  • PLC Software Modifications
  • HMI Screens Modifications
  • Commissioning Records
  • As-Built Documentation

Technical specifications

  • 20 Inputs/Outputs Addition & Changes
  • Telemecanique PLC
  • Telemecanique Panel Mount HMI