Secondary ServiceControl Systems Engineering, Control Systems Panels Design & Build, Factory & Site Acceptance Testing, Pre-Commissioning & Commissioning, SCADA HMI System Engineering, Start Up Audit Start Up & Process Optimisation
ClientCaparo Steel
Start DateJun 1990
Consultant or EPCNone
Contract Value ($)20000
Project LocationEmpson Rd, Peterborough, PE1 5UP, United Kingdom
Person Hours660
Execution OfficeBirmingham, United Kingdom
StatusCompleted
Scope of work
Re-Bar Shearline controls for production of varying Bar lengths