Description

Preparation of project specific Commissioning Procedures following OGC Commissioning & Start-up Procedure.

Scope

Lead all commissioning actvities for OGC project

  • Collect Design Inputs
  • Verify Systemisation by Consultant
  • Prepare Commissioning Plan
  • Prepare Commissioning Procedures
  • Lead Site Commissioning Activities
  • Commissioning Planning
  • Commissioning Procedure
  • OGC Commissioning & Start-up Procedure

Project Details

Contract No. C263
Industry Oil & Gas
Client Salalah Methanol Company
Consultant or EPC Zawawi Powertech Engineering
Country Oman
Primary Service Commissioning & Start-up
Secondary Service Technical Document Authoring
Start Date Aug 2017
Person Hours 330