Project Description & Scope of Work
Description
This was a 2 part project for supervising the pre-commissioning activities and responsible for safe Commissioning, Start-up and Handover processes of the project. Our Commissioning Engineers performed problem free commissioning by following structured methodologies and procedures, drawing on lessons learned, identifying and mitigating possible risks.
Part 1 was to integrate the feed streams of NGL-1 and NGL-4 Plants coming from various sources in-order to process any of the feeds in any of the fractionation trains available in NGL-1 or NGL-4 Plants.
Part 2 was the installation of New Export Fiscal Metering Systems for Propane and Butane being loaded from NGL Jetty and common export Fiscal Metering System for Condensate being loaded from NGL Jetty and MPB.
Scope
Pre-commissioning, Commissioning, Start-up and Handover processes for a USD 26 Million EPIC project for Feed Stream Integration & Fiscal Metering Systems Installation at Mesaieed, Qatar.
- Validation of Construction Completion
- Management of DCS & Safety System Modifications
- Developing Commissioning Procedures
- Conducting Pre-Commissioning Checks
- Conducting Process Commissioning
- Conduct Start-up
- Conducting Process Optimisation
- Conduct Training
- DCS & Safety System Modifications
- Commissioning Procedures
- Pre-Commissioning Records
- Commissioning Records
- Process Optimisation Records
- Alarm & Trip Records
- As-Built Documentation
- Training
A 2 part project for Feed Stream Integration & Fiscal Metering Systems:
Part 1 contained:
- 35 Piping Tie-ins to live System at NGL-1/2/3&4
- Approximately 3 Kilometres of Piping
- New ESD and SCADA Systems at NGL1/2
- Integration with existing ESD System at NGL1/2
- Integration with existing DCS and ESD Systems at NGL-3
Part 2 contained:
- 3 Export Fiscal Metering Skids
- Fiscal Metering with 14 Flow Computers
- 26 Piping Tie-ins to live Systems at NGL1/2
- Integration with existing F&G System at NGL1/2
- New SCADA system covered in part 1 above
- New UPS System
- Switchgear modification at S/S-41 at NGL2
Project Details
Contract No. | C213 |
---|---|
Industry | Oil & Gas |
Client | Qatar Petroleum |
Consultant or EPC | Panorama Contracting and Engineering Services |
Country | Qatar |
Primary Service | Commissioning & Start-up |
Secondary Service | As Built Documentation |
Start Date | Sep 2015 |
Person Hours | 3,920 |
Status | Completed |