Pernton & Newton SatCon Control System Communication Interfaces Modifications

Modifications to PLC control system communication module to send equipment status to SCADA

Project Details

  • Contract No. C118
  • Primary Service Construction & Commissioning, Detailed Design & Engineering
  • Industry Water Treatment
  • Secondary Service As Built Documentation, Pre-Commissioning & Commissioning, Safety Control Systems Engineering, Site Construction, Start Up Audit Start Up & Process Optimisation
  • Client United Utilities
  • Start Date May 2002
  • Consultant or EPC None
  • Contract Value ($) 10000
  • Project Location Richmond Row, Liverpool, L3 3BP, United Kingdom
  • Person Hours 330
  • Execution Office Birmingham, United Kingdom
  • Status Completed

Scope of work

    Modifications to PLC control system communication to send equipment status to SCADA.

Activities

  • PLC Control System Modification
  • Site Software Modification
  • Site Testing
  • Commissioning

Deliverables

  • PLC Software Modifications
  • As-Built Documentation

Technical specifications

  • 10 Inputs/Outputs Added or Changed
  • SatCon PLC