Our PDO approved Human Factors Engineering Facilitator & Scribe conducted a design review for assurance that the project design was according to PDO DEPs. A Human Factors Engineering report with design change recommendations was produced for PDO approval.

Project Details

  • Contract No. C188
  • Primary Service Consultancy
  • Industry Oil & Gas
  • Secondary Service Design Review or Audit, Human Factors Engineering
  • Client Petroleum Development Oman
  • Start Date Aug 2014
  • Consultant or EPC Special Technical Services
  • Contract Value ($) 30400
  • Project Location 539P+7X8, Al Jibal, Oman
  • Person Hours 390
  • Execution Office Muscat, Sultanate of Oman
    Birmingham, United Kingdom
  • Status Completed

Scope of work

    Facilitation of Design Review of Human Factors, produce report with design change recommendations for PDO approval.

Activities

  • Conduct Design Review Facilitation
  • Prepare Human Factors Engineering Report

Deliverables

  • Design Review Facilitation
  • Human Factors Engineering Report

Technical specifications

  • PDO DEP 30.00.60.10 - Human Factors Engineering in projects
  • PDO DEP 30.00.60.11 - Human Factors Engineering - summary of ISO standards
  • PDO DEP 30.00.60.12 - Human Factors Engineering - investment justification model
  • PDO DEP 30.00.60.13 - Human Factors Engineering - valve analysis
  • PDO DEP 30.00.60.14 - Human Factors Engineering - Application during construction
  • PDO DEP 30.00.60.15 - Human Factors Engineering - human/machine interface and control room design
  • PDO DEP 30.00.60.16 - Human Factors Engineering - attention hierarchy coding for graphical displays
  • PDO DEP 30.00.60.18 - Human Factors Engineering - Design and procurement of skid-packaged units