PDO Ghaba North Alarm Management

Project Description & Scope of Work

Description

A team of 6 engineers conducted the Alarm Rationalisation, Variable Table Conversion, Suppression & Verification for several facilities working with PDO client project engineers.

Scope

Alarm Management Rationalisation, Variable Table Conversion, Suppression & Verification for 41,500 alarms in several facilities.

  • Rationalise Alarms following DEP, Guidelines and an Alarms Philosophy
  • Produce Variable Tables
  • Produce Suppression Tables
  • Verification of alarms after implementation by system vendor
  • Alarms Philosophy
  • Rationalise Alarms
  • Variable Tables
  • Suppression Tables
  • Alarms Implementation
  • Alarms Verification
  • 41500 Alarms Implemented
  • ISA18.2 Standard
  • EEMUA 191 Standard
  • PDO Guideline GU513
  • PDO DEP 32.80.10.14 Alarm Management

Project Details

Contract No. C253
Industry Oil & Gas
Client Petroleum Development Oman
Consultant or EPC Tebodin Bilfinger
Country Oman
Primary Service Alarm Management Facilitation, Rationalisation or Implementation
Secondary Service Alarm Management Rationalisation
Start Date Oct 2017
Person Hours 5,250
Status Completed