Project Description & Scope of Work
Description
All Local and Regional Gas Control Rooms were unified at the new Gas CCR. All DCS systems Operator screens were collected, analysed and a unified Graphics Philosophy, Functional and Detailed Design documents produced for PDO approval. On approval these were used to develop and implement the unified screens at the new CCR and followed with Operator Training.
Scope
Development of Level 3 unified Operator Display Screens from Yokogawa, Emerson and Honeywell DCS systems.
- Collection of DCS Operator Screens
- Analysis of existing DCS Operator Screens
- Development of a Graphics Design Philosophy
- Development of a Graphics Functional Design Specification
- Development of a Graphics Detailed Design Specification
- Development of new screens for each DCS system
- Implementation & Testing of unified screens
- Conduct Training
- Graphics Design Philosophy
- Graphics Functional Design Specification
- Graphics Detailed Design Specification
- New Unified Screens
- Testing
- Training
- 4 DCS Systems
- 235 New Unified Screens
Project Details
Contract No. | C179 |
---|---|
Industry | Oil & Gas |
Client | Petroleum Development Oman |
Consultant or EPC | Honeywell Oman |
Country | Oman |
Primary Service | Control & Safety Systems Integration |
Secondary Service | None |
Start Date | Feb 2014 |
Person Hours | 10,010 |
Status | Completed |