UK Phone: +44 870 701 9131

Oman Phone: +968 2209 4081 ▪ Pakistan Phone: +92 301 8620669

PDO Commissioning Systemisation, Commissioning Completion & Commissioning

Project Description & Scope of Work

Description

Several projects document inputs were collected and Commissioning Systemisation conducted with preparation of applicable pre-commissioning check sheets and commissioning procedures at Wood Group CC offices in Muscat. These were then issued to our commissioning team at site to Commissioning and Start-up of the facilities new and upgrade projects.

Scope

Commissioning Systemisation, Commissioning Completions & Commissioning of 141 PDO South Asset Projects.

  • Collect Design Inputs including PEFS
  • Conduct Systemisation
  • Prepare Applicable Check Sheets
  • Prepare Commissioning Procedures
  • Conduct Pre-Commissioning Checks
  • Update CCMS Commissioning Management System
  • Conduct Commissioning
  • Conduct Start-up
  • Commissioning Systemisation
  • Project Commissioning Packs
  • Pre-Commissioning
  • Commissioning
  • Start-up
  • Systemisation for 141 Projects
  • PDO PR 1159 Commissioning & Start-up Procedure

Project Details

Contract No. C165
Industry Oil & Gas
Client Petroleum Development Oman
Consultant or EPC Wood Group
Country Oman
Primary Service Commissioning & Start-up
Secondary Service Completions Systems
Start Date Mar 2013
Person Hours 21,890
Status Completed