PDO Amal Steam Alarm Rationalisation

PDO engaged us to implement the previously rationalised alarms by liaising with the systems vendor.

Project Details

  • Contract No. C221
  • Primary Service Consultancy, Implementation
  • Industry Oil & Gas
  • Secondary Service Alarm Management Implementation, Alarm Management Rationalisation
  • Client Petroleum Development Oman
  • Start Date Feb 2016
  • Consultant or EPC Special Technical Services
  • Contract Value ($) 102600
  • Project Location 8MMM+CMV, Amal, Oman
  • Person Hours 2640
  • Execution Office Muscat, Sultanate of Oman
  • Status Completed

Scope of work

    Implementation of 10,400 Rationalised Alarms.

Activities

  • Utilise Rationalised Alarms Variable Table to verify alarms implementation by system vendor

Deliverables

  • Alarms Implementation
  • Alarms Verification

Technical specifications

  • 10400 Alarms Implemented
  • ISA18.2 Standard
  • EEMUA 191 Standard
  • PDO Guideline GU513
  • PDO DEP 32.80.10.14 Alarm Management