PDO Amal HRSG 1C Alarm Management Rationalisation & Variable Table Conversion

PDO engaged us to do a Variable Table Conversion and implement the rationalised alarms by liaising with the systems vendor.

Project Details

  • Contract No. C248
  • Primary Service Consultancy, Implementation
  • Industry Oil & Gas
  • Secondary Service Alarm Management Implementation, Alarm Management Rationalisation
  • Client Petroleum Development Oman
  • Start Date May 2018
  • Consultant or EPC None
  • Contract Value ($) 40000
  • Project Location 8MMM+CMV, Amal, Oman
  • Person Hours 1030
  • Execution Office Muscat, Sultanate of Oman
  • Status Completed

Scope of work

    Alarm Management Rationalisation and Variable Table Conversion for 4,100 alarms.

Activities

  • Utilise Rationalised Alarms Variable Table to verify alarms implementation by system vendor

Deliverables

  • Alarms Implementation
  • Alarms Verification

Technical specifications

  • 4100 Alarms Implemented
  • ISA18.2 Standard
  • EEMUA 191 Standard
  • PDO Guideline GU513
  • PDO DEP 32.80.10.14 Alarm Management