PDO Alarm Facilitation Services Blanket 1 Year Contract

A team of 6 engineers conducted the Alarm Rationalisation, Variable Table Conversion, Suppression & Verification for several facilities working with PDO project engineers.

Project Details

  • Contract No. C219
  • Primary Service Consultancy, Implementation
  • Industry Oil & Gas
  • Secondary Service Alarm Management Facilitation, Alarm Management Implementation, Alarm Management Rationalisation
  • Client Petroleum Development Oman
  • Start Date Dec 2015
  • Consultant or EPC None
  • Contract Value ($) 220600
  • Project Location Al Fahal Street, Muscat 100, Oman
  • Person Hours 2830
  • Execution Office Muscat, Sultanate of Oman
  • Status Completed

Scope of work

    Alarm Management Rationalisation, Variable Table Conversion, Suppression & Verification for 22,400 alarm in several facilities.

Activities

  • Rationalise Alarms following DEP, Guidelines and an Alarms Philosophy
  • Produce Variable Tables
  • Produce Suppression Tables
  • Verification of alarms after implementation by system vendor

Deliverables

  • Alarms Philosophy
  • Rationalise Alarms
  • Variable Tables
  • Suppression Tables
  • Alarms Implementation
  • Alarms Verification

Technical specifications

  • 22400 Alarms Implemented
  • ISA18.2 Standard
  • EEMUA 191 Standard
  • PDO Guideline GU513
  • PDO DEP 32.80.10.14 Alarm Management