Project Description & Scope of Work
Description
Full Paint Shop and Mix Room Control System including Paint Mix Room and 2 full Paint Lines.
Scope
New Paint Shop and Mix Room control system
- PLC & SCADA Control System Design
- Software Development
- Factory Acceptance Testing
- Commissioning
- Conduct Start-up
- PLC Software
- SCADA Screens Design
- Factory Acceptance Test Report
- Alarm & Trip Settings
- Commissioning Records
- 4,000 Inputs/Outputs
- 8 Rockwell PLCs with high speed co-processors
- 4 Panel Mount HMIs
- EDDI Ford software programming style
- 2 SCADA systems
- 2 Paint Lines
- 2 Base Coat Durr Bell Stations
- 2 Reciprocator Durr Machines
- 2 Clear Coat Durr Bell Station
- 2 Underbody Wax units
- Track and Oven Control
Project Details
Contract No. | C072 |
---|---|
Industry | Automotive |
Client | Auto Europa |
Consultant or EPC | Durr |
Country | Portugal |
Primary Service | Control & Safety Systems Integration |
Secondary Service | Commissioning & Start-up |
Start Date | Aug 1993 |
Person Hours | 4,920 |
Status | Completed |