Modernization of Control Room

Design, Engineering, demolition, installation, commissioning & startup with parallel operations for the modernisation of the main control room and OTS room.

Project Details

  • Contract No. C292
  • Primary Service Construction & Commissioning, Detailed Design & Engineering
  • Industry Oil & Gas
  • Secondary Service As Built Documentation, Commissioning Management, Construction Management, Control Systems Engineering, Projects Plans Procedures Specifications & Detailed Designs, SCADA HMI System Engineering, Site Construction, Start Up Audit Start Up & Process Optimisation
  • Client OQ Methanol
  • Start Date Sep 2020
  • Consultant or EPC None
  • Contract Value ($) 634249
  • Project Location WXPR+P49, Raysut, Oman
  • Person Hours 2000
  • Execution Office Muscat, Sultanate of Oman
    Birmingham, United Kingdom
  • Status Completed

Scope of work

    Design, Engineering, demolition, installation, commissioning & startup with parallel operations

Activities

  • Site Survey
  • Detailed Design
  • Demolition
  • Installation
  • Commissioning & Startup with Parallel Operations

Deliverables

  • Engineering Design
  • Demolition
  • Installation
  • Commissioning & Startup with Parallel Operations

Technical specifications

  • OQ Standards