Secondary ServiceAs Built Documentation, Control Systems Engineering, Projects Plans Procedures Specifications & Detailed Designs, Safety Control Systems Engineering, Technical Document Authoring
ClientDaleel Petroleum
Start DateNov 2020
Consultant or EPCNone
Contract Value ($)338673
Project LocationH9RC+MW8, Muscat, Oman
Person Hours11290
Execution OfficeMuscat, Sultanate of Oman
StatusCompleted
Scope of work
Site Survey
As-Built Documentation
CAD Drawings
Activities
Site Survey
Verify correct information on site on Master Drawings.
Verify if Panels in Project Drawings and incorporate in Master Drawings.
Verify if the field instrument in Project Drawings and incorporate in the Master Drawings.
Verify the P&IDs at site. Survey of P&IDs limited to determining whether the piping lines, instrument and process equipment shown in the P&IDs are existing or non-existing and update Master Drawings.
Technical information like control scheme, process concept etc. detailed by Abalto during survey of the P&IDs.
Any Red Line Mark Ups will be in red pen. Any deletion will be in blue.