Daleel Site Survey

Conduct a site survey and verify that all site equipment is captured on Master Drawings, producing Master CAD Drawings.

Project Details

  • Contract No. C300
  • Primary Service Construction & Commissioning, Detailed Design & Engineering
  • Industry Oil & Gas
  • Secondary Service As Built Documentation, Control Systems Engineering, Projects Plans Procedures Specifications & Detailed Designs, Safety Control Systems Engineering, Technical Document Authoring
  • Client Daleel Petroleum
  • Start Date Nov 2020
  • Consultant or EPC None
  • Contract Value ($) 338673
  • Project Location H9RC+MW8, Muscat, Oman
  • Person Hours 11290
  • Execution Office Muscat, Sultanate of Oman
  • Status Completed

Scope of work

  • Site Survey
  • As-Built Documentation
  • CAD Drawings

Activities

  • Site Survey
  • Verify correct information on site on Master Drawings.
  • Verify if Panels in Project Drawings and incorporate in Master Drawings.
  • Verify if the field instrument in Project Drawings and incorporate in the Master Drawings.
  • Verify the P&IDs at site. Survey of P&IDs limited to determining whether the piping lines, instrument and process equipment shown in the P&IDs are existing or non-existing and update Master Drawings.
  • Technical information like control scheme, process concept etc. detailed by Abalto during survey of the P&IDs.
  • Any Red Line Mark Ups will be in red pen. Any deletion will be in blue.

Deliverables

  • Site Survey
  • As-Built Documentation
  • CAD Drawings

Technical specifications

  • Daleel Petroleum Standards