Project Description & Scope of Work
Description
Upgrade the control system for timed control of Limitorque de-sludging valves with status feedback to HMI.
Scope
Control system upgrade for addition of controls decanting value to settlement tanks.
- Limitorque Control System Modification
- Site Software Modification
- Site Panel Modifications
- Site Testing
- Commissioning
- Conduct Start-up
- Limitorque Controller Software Modifications
- HMI Screens Modifications
- IO Testing Records
- Alarm & Trip Settings
- Commissioning Records
- 50 Inputs/Outputs Addition & Changes
- Limitorque Controllers
- HMI Panel Display
Project Details
Contract No. | C079 |
---|---|
Industry | Water |
Client | Severn Trent Water |
Consultant or EPC | Purac |
Country | United Kingdom |
Primary Service | Control & Safety Systems Integration |
Secondary Service | Technical Document Authoring |
Start Date | Feb 1997 |
Person Hours | 330 |
Status | Completed |