Chelmsford Waste Water Treatment Works SCADA System Upgrades

Modify SCADA reports to client requirement to show and print daily, weekly and monthly production totals.

Project Details

  • Contract No. C103
  • Primary Service Construction & Commissioning, Detailed Design & Engineering, Implementation
  • Industry Water Treatment
  • Secondary Service As Built Documentation, Control Systems Engineering, Factory & Site Acceptance Testing, Pre-Commissioning & Commissioning, Projects Plans Procedures Specifications & Detailed Designs, SCADA HMI System Engineering, Start Up Audit Start Up & Process Optimisation
  • Client Anglian Water
  • Start Date Mar 2001
  • Consultant or EPC Purac
  • Contract Value ($) 5000
  • Project Location Brook End Rd S, Chelmsford, CM2 6NZ, United Kingdom
  • Person Hours 170
  • Execution Office Birmingham, United Kingdom
  • Status Completed

Scope of work

    Upgrades to SCADA system Reports

Activities

  • Site SCADA Software Modification
  • Site Testing

Deliverables

  • New & Modified SCADA Reports
  • Training

Technical specifications

  • Intouch SCADA