Project Description & Scope of Work
Description
Control system and software design and development for a continuous batch process control of Sludge Pasteurisation Plant. System controlled by an Allen Bradley PLC interfaced to a PanelView. The control philosophy involved the sludge heating using heating and recovery coil heat exchangers to 72°C and holding the sludge for 30 minutes to kill pathogens for sludge disposal to land fill. Residual heat recovery was use to heat incoming ambient sludge with heat exchangers. Sludge flow and heat to digesters was also improved and managed.
Scope
Provision of Sludge Pasteurisation Plant control system.
- PLC & SCADA Control System Design
- Software Development
- Control Panel Design & Build
- Factory Acceptance Testing
- Commissioning
- Conduct Start-up
- PLC Software
- SCADA Screens Design
- Factory Acceptance Test Report
- Commissioning Records
- As-Built Documentation
- Training
- 120 Inputs/Outputs
- Allen Bradley SLC 500
- Intouch SCADA system
Project Details
Contract No. | C115 |
---|---|
Industry | Water |
Client | Anglian Water |
Consultant or EPC | Purac |
Country | United Kingdom |
Primary Service | Control & Safety Systems Integration |
Secondary Service | Commissioning & Start-up |
Start Date | Mar 2002 |
Person Hours | 2,630 |
Status | Completed |