Project Description & Scope of Work
Description
Commissioning for a complete 500 MLD Waste Water Treatment Works.
Scope
Commissioning of a complete end-to-end 500 MLD Waste Water Treatment plant.
- Site Acceptance Testing
- Commissioning
- Conduct Start-up
- Process Optimisation
- Site Acceptance Test Report
- Alarm & Trip Settings
- Commissioning Records
- As-Built Documentation
- Training
- 1,600 Inputs/Outputs
- 8 Allen Bradley 5/60e PLCs
- 2 RS View 32 Hot Standby SCADA Systems
- 8 HMI PanelView 2711 Displays
- Dual redundant fibre optic network
- Rotating Bar Interceptors
- Inlet Screens
- Grit Settlement Bend Variable Speed Drives
- 4 Settlement Tanks
- BAFF Plant Blowers
- 2 Buffer Tanks
- 2 Digesters
- 2 Pathogen Kill Tanks
- 2 Centrifuges
- Odour Control Bed
- Final Effluent Discharge Variable Speed Drives
Project Details
Contract No. | C110 |
---|---|
Industry | Water |
Client | United Utilities |
Consultant or EPC | Purac |
Country | United Kingdom |
Primary Service | Control & Safety Systems Integration |
Secondary Service | Commissioning & Start-up |
Start Date | Jun 2001 |
Person Hours | 3,280 |
Status | Completed |