Located on a previously undeveloped desert site 350 kilometres south of Muscat, work on the Khazzan tight gas project began in 2014 and the completed development will eventually contribute roughly a third of Oman’s natural gas supply.
Project Details
Contract No.C238
Primary ServiceConstruction & Commissioning
IndustryOil & Gas
Secondary ServiceAs Built Documentation, Commissioning Management, Commissioning Planning Systemisation & Completion, Manpower Supply, Site Construction, Start Up Audit Start Up & Process Optimisation
ClientBritish Petroleum
Start DateMay 2017
Consultant or EPCPetrofac
Contract Value ($)132000
Project LocationOman
Person Hours2540
Execution OfficeMuscat, Sultanate of Oman
StatusCompleted
Scope of work
All Instrumentation Pre Commissioning and Commissioning and initial operation and maintenance